Well, enough of this nonsense.
Here's the answer to why you need only about 4.5" (actually, less than that will do) of westward push in beam B1 (below) in order for the girder to walk off both the seat & the support plate.
Tony, C7 & gerrycan have been made the patently false assumption that all of the relative motion between the girder & the seat is achieved by moving the girder to the west.
This is only 1/2 of the relative motion between the two parts.
Here is a drawing of the Northeast quadrant of WTC7 to get oriented.
Note: All single story images are the 13th floor for the Case B temperatures.
A compass rose is at the center top for directions.
As noted, beams are labeled B#, Columns are labeled C# & Girders are labeled G#. (Where # is a number.)
Note well that all of the EW beams attach to (& push) girders, and none to C79.
Note well that girder G2 attaches to (& push) C79.
Now look at this diagram of the heating sequence on floor 13:
It shows that the fires approached Col 79 from the south and on the east side of the Girders between Column 80 & Column 44.
Here is a drawing of the damage to the connectors & beams between 3.7 & 4.0 hours.
The heat clearly fractured the shear studs between the concrete & beams on the east side of the girder line between C80 & C44. The fires & heat also fractured most of the connections between the beams & girders on the east side of the girders, and buckled some of the beams.
All of the connections between the girders & Col 79 have been sheared, with the exception of the connection to Girder G2 in this diagram.
This means that Column 79 is completely free to deflect towards the east on this floor.
When beam B1 heats up, it pushes on Girder G1, moving its end generally towards the west (actually WNW). The end of girder G1 is going to move in an arc, with the center of the arc being the closest intact connection to one of the B2, B3, etc Beams, north of C79.
After all of the bolts on the east side of G1 & the beam between C79 & C80 have been sheared, then the fire moves westward to the interior, right under Girder G2, as shown at 5:30 & 6:00 pm in the concrete slab temp drawings.
When girder G2 heats up, it pushes C79 (right at vertical location of the G1 seat) towards the ESE.
The relative motion between the end of girder G1 & its seat on C79 is the SUM of these two motions.
You guys have only been considering the first component, assuming C79 does not move. This is wrong.
And since it looks like the length of girder G2 is approximately the same as B1, and the temp reached by girder G2 is approximately the same as the temps reached by B1, then the deflection of the relatively free moving column C79 should be approximately the same as the deflection of the end of girder G1. Essentially approximately doubling the Girder G1 to seat movement.
To a first order approximation, 4.5" of B1 motion will result in about 9" of total relative motion between Girder G1 & its seat.
I can easily see an amateur ignoring the expansion of G2. But that could easily be considered a "howler" if an allegedly experienced mechanical engineer were to do so.
Your turn, Tony.
Here's the answer to why you need only about 4.5" (actually, less than that will do) of westward push in beam B1 (below) in order for the girder to walk off both the seat & the support plate.
Tony, C7 & gerrycan have been made the patently false assumption that all of the relative motion between the girder & the seat is achieved by moving the girder to the west.
This is only 1/2 of the relative motion between the two parts.
Here is a drawing of the Northeast quadrant of WTC7 to get oriented.
Note: All single story images are the 13th floor for the Case B temperatures.
A compass rose is at the center top for directions.
As noted, beams are labeled B#, Columns are labeled C# & Girders are labeled G#. (Where # is a number.)
Note well that all of the EW beams attach to (& push) girders, and none to C79.
Note well that girder G2 attaches to (& push) C79.
Now look at this diagram of the heating sequence on floor 13:
It shows that the fires approached Col 79 from the south and on the east side of the Girders between Column 80 & Column 44.
Here is a drawing of the damage to the connectors & beams between 3.7 & 4.0 hours.
The heat clearly fractured the shear studs between the concrete & beams on the east side of the girder line between C80 & C44. The fires & heat also fractured most of the connections between the beams & girders on the east side of the girders, and buckled some of the beams.
All of the connections between the girders & Col 79 have been sheared, with the exception of the connection to Girder G2 in this diagram.
This means that Column 79 is completely free to deflect towards the east on this floor.
When beam B1 heats up, it pushes on Girder G1, moving its end generally towards the west (actually WNW). The end of girder G1 is going to move in an arc, with the center of the arc being the closest intact connection to one of the B2, B3, etc Beams, north of C79.
After all of the bolts on the east side of G1 & the beam between C79 & C80 have been sheared, then the fire moves westward to the interior, right under Girder G2, as shown at 5:30 & 6:00 pm in the concrete slab temp drawings.
When girder G2 heats up, it pushes C79 (right at vertical location of the G1 seat) towards the ESE.
The relative motion between the end of girder G1 & its seat on C79 is the SUM of these two motions.
You guys have only been considering the first component, assuming C79 does not move. This is wrong.
And since it looks like the length of girder G2 is approximately the same as B1, and the temp reached by girder G2 is approximately the same as the temps reached by B1, then the deflection of the relatively free moving column C79 should be approximately the same as the deflection of the end of girder G1. Essentially approximately doubling the Girder G1 to seat movement.
To a first order approximation, 4.5" of B1 motion will result in about 9" of total relative motion between Girder G1 & its seat.
I can easily see an amateur ignoring the expansion of G2. But that could easily be considered a "howler" if an allegedly experienced mechanical engineer were to do so.
Your turn, Tony.
Last edited:
