So I tried to understand gerrycan's claim:
The figure that you chose use shows only horizontal connection damage and you failed to mention that. It shows that the C79 south and west connections have no damage and that the C79-44 girder connection has failed horizontally.
The corresponding figure which in the draft report is directly below yours, shows connection damage vertically and that the connection between the girder and column 79 had sustained no damage.
For context, this part of the thread was discussing whether column 79 could have displaced eastwards, as NIST claims, and gerrycan was disputing it saying that the column was "heavily restrained" by H3016, P3016 and B2002:
Because the column is heavily restrained. Granted that between beam k3004 to the NE of the column, and beam D3004 to the SE of the column there is no beam tying C79 to C38, there is however H3016, P3016, and B2002, all heavily restraining the column.
That's the post that I replied to, and my reply is what gerrycan disputed.
Now, this is a map of where to locate these three elements:
H3016 is the beam west of the girder in question, P3016 is the short beam that connects to the center of said girder, and B2002 is the girder between columns 80 and 81. gerrycan essentially said that these elements prevented horizontal movement of the column to the east.
I downloaded the draft report to know what gerrycan was talking about, and I found that in it, NIST shows no damage to the connection at the C79 side of the girder between C44 and C79
in the vertical direction, but it failed
in the horizontal direction. I don't know if that is a mistake in the final report, because the seat didn't fail (NIST made it rigid, to start with), and I don't know if the walk-off happened before or after the 4 hours shown in that figure.
But most importantly, that's irrelevant to the argument. The fact that the connection had failed horizontally is enough for the girder between C44 and C79 to not restrain C79 from moving east, therefore neither beam P3016 nor the state of the girder connection in the vertical direction are relevant to the restraining of the column.
The other beam that gerrycan mentioned was H3016, whose connection, together with that of two of its neighbours, was completely failed horizontally. Therefore it could not restrain the girder between C76 and C79 from expanding (I can't see how it could have done it in the first place, anyway), and from pushing C79 east and C76 west as NIST said it did.
The girder between C79 and C80 was buckled, as was the other element that gerrycan mentioned that was restraining C79, namely girder B2002 between C80 and C81, which I can't see in which way could it restrain the girder.
So no, the column was not "heavily restrained". The only thing that could restrain it from moving east due to the push of the girder between C76 and C79, is the buckled girder between C79 and C80, namely A2002, which wasn't in a good angle to restrain that movement anyway.
I think that there are only two explanations for gerrycan bringing that up:
- Desperately trying to kill the messenger.
- Missing the context of my reply, which was about horizontal restraint of C79.