Mirror Segment Deployment Tracker
Nominal Event Time: Launch + 18-28 days
Status: Ongoing
The adjacent image tracks the progress of the individual primary mirror segments (A,B,C) and the secondary (SM) mirror as they move upward 12.5mm from their stowed launch position to a deployed state where they are ready for the mirror alignment process. View a full screen copy.
The mirrors move in very small increments over the course of ~10 days to complete their deployment. They move approximately 1mm per day each. For more detail on this process read this blog entry.
Each primary mirror segment has an ID which consists of a letter (A,B,C) followed by a number. The letter denotes one of 3 different 'prescriptions' for each group of primary mirror segments.
NOTE: Segment A3 and A6 will be moved separately at the end of the process because their position sensors are read out in a different way.